You are:News Center > News Center
At 9:00 a.m. on March 4, the first modular of Sanmen Power Station Phase II was officially Started.
This module is a steel structure assembly module with air duct. We transfer the operation from the site to the prefabrication plant, and carry out the 3D exercise of the BIM model in advance to integrate the manufacturing and installation requirements into the BIM model. Before welding and installation, various requirements were considered as a whole, and close communication with the civil steel structure discipline was carried out to realize the integrated thinking of the whole discipline and the whole process, ensuring the safe and orderly implementation of the installation and construction activities.
Sanmen Power Station Phase II is a follow-up to successfully undertake the project Phase I. The project Phase II will build 2 set of 1,000MW plants. After putting into operation, the capacity will reach 5,000MW, and the annual power generation is expected to reach 40 billion kWh.
International Engineering Division